Robotic stacker requires a control system upgrade from an existing legacy Siemens S7-300 PLC rack to TIA Portal. The scope covers hardware replacement, program migration, and full on-site commissioning.
- Replace existing Siemens S7-300 rack including power supply, CPU, Profibus connections, and associated digital/analog I/O modules
- Migrate existing control program and logic to Siemens TIA Portal
- Rewire, terminate, and verify existing control wiring to the new PLC hardware
- Perform I/O loop checking, functional testing, and stacker commissioning
- Plan for 80 hours of work on site between 14 December 26 and 25 December 26
Nachweisfotos
Need to exchange S7 PLC for TIA portal.
Anforderungen und Fähigkeiten
Technisch
PLC Automation
Plc Migration (S7 To TIA)
Siemens TIA Portal
Commissioning & Startup
PLC Programming
Electrical Wiring
Electrical Troubleshooting
Fieldbus Communication (Modbus/Profibus)
Electrical Schematic Reading
Ladder Logic Interpretation
Control Panel Building
Marken
Mesh
Branche
Robotics - Industrial
Maschinentypen
Robotic StackerRobotics - Industrial
Art der Arbeit
Inbetriebnahme
Standortvorgaben
Hard hatESD protectionLOTO certificationHi Vis vest